REPAIR GROUTING USING BATTU

Repair Grouting Training Video

Application Scope

Suitable for repairing non-structural cracks, surface defects, honeycombing, spalled concrete, and localized damaged concrete areas.

Step 1: Surface Preparation

Remove all loose concrete, dust, gravel, and contaminants from the repair area.

Step 2: Crack Opening

Using a concrete grinder, widen the crack into a "V" groove approximately 18–25 mm deep, depending on the extent and depth of the defect. Ensure the groove is deep for repair material placement.

Step 3: Cleaning and Pre-Wetting

Thoroughly clean the inside of the groove and surrounding area. Saturate the exposed groove with clean water before commencing repairs.

Step 4: Preparation of Bonding Slurry

Mix 1 kg of cement with 50 ml of BATTU. Add sufficient water to prepare a smooth, brushable cement slurry.

Step 5: Application of Bonding Slurry

Using a brush, apply a uniform coat of the prepared slurry onto all exposed surfaces within the repair groove. This slurry acts as a bonding bridge between the existing concrete and the repair mortar.

Step 6: Preparation of Repair Mortar

Prepare a repair mortar by mixing 1 part cement with 3 parts clean, well-graded sand (1:3 ratio). Add 100 ml of BATTU for every 1 kg of cement used and mix thoroughly. Add water gradually to obtain a tight, bendable, workable micro-concrete consistency.

Step 7: Placement and Compaction

Immediately place the repair mortar into the prepared groove while the bonding slurry remains sticky. Compact thoroughly using suitable tools to eliminate air pockets and ensure complete filling of the repair cavity.

Step 8: Surface Finishing & Protective Slurry Coat

Finish the repaired area flush with the surrounding and apply a final coat of the bonding slurry over the repaired surface using a brush to improve surface integrity and protection.

Step 9: Curing

Protect the repaired area with wet gunny bags, cloth or equivalent curing methods. Maintain continuous curing for a minimum of 2-3 days, extending the duration under hot, dry, or windy weather conditions.

High Bonding High Bonding
Cracking Resistance Cracking Resistance
Water Resistance Water Resistance
High Pull Out Strength High Pull Out Strength

Critical Control Points

  • Ensure all loose and deteriorated concrete is removed before repair.
  • Maintain the substrate in hydrated condition before application.
  • Apply repair mortar while the bonding slurry is still sticky.
  • Compact thoroughly to avoid voids and honeycombing.
  • Adequate curing is essential for optimum bond strength and durability.

Expected Benefits

  • Strong bond with existing concrete.
  • Reduced shrinkage cracking.
  • Improved durability of repaired areas.
  • Enhanced water resistance.
  • Better resistance to future deterioration.
  • Improved long-term performance of repaired concrete.

Scan QR Code

Open This Repair Grouting Guide on Your Phone

Scan this QR code to open the BATTU Repair Grouting application guide directly on your phone.

https://battu.co.in/repair-grouting
BATTU Repair Grouting QR Code